Drop shafts 2,6 and 7 are moving into their final stages. Week of Dec-11
At drop shaft #2 below (Waldron Circle) the vortex was installed this week. Below is a wide shot showing the space it will be lowered into and here is a video link of the lower from 12-10-20. https://youtu.be/1u0sbNtOm2w
At drop shaft #6 below (Camp Allen) crews working to restore. Photo on right shows progress at drop shaft #5 (Thieme Drive) where workers continue installing support beams.
Week of Dec-11
At drop shaft #7 below (Guldlin Park) crews removed dewatering pumps, compacted sand and tested the compaction. Photo on the right shows drop shaft #3 (Brown Street/Hale Avenue) where crewxcavation continues around the drop shaft.
Week of Dec-11