Hale Avenue Phase III

The working shaft is down about 220 feet this week and pump station shaft about 190 feet. The neighborhood drop shafts are seeing a lot of activity and will be busy next week. At Hale Avenue crews will begin phase III lining, Camp Allen is at phase II – augers will continue through rock and the steel casing insertion at East Central Park. View work at shaft site