Journey is 70% Complete

MamaJo’s journey is 70 percent complete.  Today she’s about 300 feet north of Taylor Street.  Meanwhile related work in neighborhoods along the St. Marys and Maumee River continues with drop shaft and consolidation sewer work.

Below – Photo on left shows crews pouring the mud mat at drop shaft 5 (Thieme Drive) so they can continue work.  The work on Thieme is two projects the drop shaft and a consolidation sewer. On the right we see the wall being formed inside drop shaft 1 (Foster Park). January 8-14, 2021.

spreading mud
forming wall

Below work at drop shaft 2 (Waldron Circle) shows crews working on the duct bank on the left and photo on the right is of workers installing bolts on vent. January 8-14, 2021.

pour duct bank
installing bolts

Consolidation sewer under the St. Marys River, near the Harrison Street Bridge sees crews pouring placing forms below the river level and pouring flowable fill over pipes installed. January 8-14, 2021.

transition structure
pouring flowable fill