Jefferson Blvd. Water Main Replacement

Page last updated May 18, 2026

UPDATE: As of May 18, barricades and cones have been picked up along W Jefferson Boulevard. Construction will now begin in the Westwood Fairway neighborhood.

  • At least one eastbound and one westbound lane will remain open at all times.
  • The inside lanes (closest to the center) on both sides of the road will be open to through traffic.
  • Where turn lanes exist, they will be used as work zones.
  • When a turn lane is used for construction, the adjacent travel lane will serve as the temporary turn lane.
  • Be sure to take extra time in the morning when travelling or plan for an alternate route.

See below for weekly progress photos.

Map of W. Jefferson Blvd lane restriction. To enlarge, see below.

Project Overview

The Westwood Fairway Water Main Replacement project will bring in more than 9,000 feet of new water main pipe. This area, specifically along W. Jefferson Boulevard, has had 15 water main breaks in the last 30 years. This project will also cover N Washington Road, at the intersections of Taylor Street and Ardmore Avenue.

The area currently has cast iron water mains in place. They will be replaced with high density polyethylene pipe which is flexible and durable. Property restoration will take place following the competition of the project.

Traffic: 

This project will include lane closures or restrictions. Check back here for traffic updates and visit TrectheFort for more information. 

Contact

Sabrina Tucker

Construction Manager

Bulldozer on the side of the road digging in the grass for water main pipe.
Week 5: Digging in ground for pipe replacement
View of a dug out with water main pipes being fused together.
Week 5: Water main pipe being fused together.
Crew worker in dug out pit along construction site, surrounding by construction equipment and water pipe.
Week 5: Crew worker in water-main dug out.
Close-up of stillwater in construction site with muddy water.
Week 3: Water in construction site preparing to be vacuumed.
Workers working with vacuum on a busy street, draining out stillwater in construction hole.
Week 3: Vacuuming out excess still-water in construction site.
Shot of a new water pipe being placed by a bulldozer on a busy street.
Week 3: Close-up of new water main pipe
Two construction crew members watching machine jackhammer concrete underground.
Week 1: Jackhammering concrete
Construction crews on the side of the road digging up a hole.
Week 1: Holes being dug out
A stack of polyethelene water main pipe in a field of grass.
Week 1: New water pipe delivered
A Google Map overview of the Westwood Fairway Water Main project.
Entire Westwood Fairway Project Area
A project map overview of the W. Jefferson lane restriction.
Map of W. Jefferson Blvd lane restriction.
A blue line indicating W Jefferson Boulevard for the Westwood Fairway project.
W Jefferson Project Area
A collection of new water main pipes stacked up on top of each other on a yard in the North Anthon water main replacement.
Example of polyethylene pipes