Installing rail system extension.
Tuesday Jun 25, 2019
Tuesday Jun 25, 2019
Installing rail system extension.
Monday Jun 24, 2019
As MamaJo moves further away from the Working Shaft -- the rails system is essential to take workers to their daily job. The...
Saturday Jun 22, 2019
Photo below is looking down the drop shaft located at Headwaters Park West. There are 7 drop shafts along the five mile route...
Thursday Jun 20, 2019
Follow MamaJo's story on the new Story Map. Click this link MamaJo Story Map
Friday Jun 14, 2019
Photos show the additional slurry circuit installed and the segments being delivered via rail car into the tunnel for unloading.
Thursday Jun 13, 2019
Permanent vent line was installed and is now connected to the gantry 12 (end of MamaJo, the Tunnel Boring Machine).
Thursday Jun 6, 2019
MamaJo workers are extending the slurry lines and second photo looks down working shaft as final piece of MamaJo is in place. (photos...
Tuesday Jun 4, 2019
Worker inside MamaJo installs segment ring in tunnel at Dwenger Avenue.
Monday Jun 3, 2019
First holes being drilled at Foster Park retrieval shaft.
Thursday May 30, 2019
Lots of work going on around town -- below truck delivers equipment to retrieval shaft at Foster while crews are lining the drop...