Workers scaling retrieval shaft walls at the Foster Park location.
Wednesday May 29, 2019
Wednesday May 29, 2019
Workers scaling retrieval shaft walls at the Foster Park location.
Thursday May 9, 2019
Work continues as MamaJo moves forward to continue adding on the additional gantries. This week's photos show crews connecting Gantry 6 and the...
Friday Apr 19, 2019
MamaJo’s first cut into bedrock. Click on this link to see sheared rock coming out. MamaJo’s first cut into bedrock April 19 Click…
Monday Apr 15, 2019
Gantries move the concrete liner pieces forward on a conveyor. Each piece will be attached and connected to make a ring. Click on...
Monday Apr 1, 2019
View of inner pieces #2 and 3 are attached. These are the precast concrete pieces we showed in earlier photos. Once attached, they...
Wednesday Mar 27, 2019
Photo below shows first liner pieces being connected. Crews are working in the Tunnel Boring Machine.
Wednesday Mar 20, 2019
Photo below shows the gantries placed in the pump station area. The pump station is just east of the working shaft where parts...
Tuesday Mar 12, 2019
Photo below shows three parts of MamaJo connected and preparing for the five mile journey.
Monday Feb 11, 2019
Last week two pieces of MamaJo were sent down the working shaft. The photo below shows the machine after some of the connections...
Monday Feb 4, 2019
Construction crews began lowering MamaJo through the working shaft on Dwenger Avenue. High winds and sub-zero temperatures delayed lowering Mamajo, because of the...