Progress continued at the two neighborhood drop shaft sites and at the working shaft sight. Late in the week, heavy-rain slowed the project.…
Friday Jun 22, 2018
Friday Jun 22, 2018
Progress continued at the two neighborhood drop shaft sites and at the working shaft sight. Late in the week, heavy-rain slowed the project.…
Friday Jun 15, 2018
The Drop Shaft at Camp Allen, near Main Street and the St. Marys River, is moving along. This week a 50-ton casing was...
Friday Jun 8, 2018
The working shaft and the pump station shaft are progressing on Dwenger Avenue. The working shaft is at about 130 feet and pump...