MamaJo is closing in on the 4-mile mark. Currently she’s drilled 20,637 feet with another 3,927 go -- just under 3/4 of a...
Friday Mar 26, 2021
Friday Mar 26, 2021
MamaJo is closing in on the 4-mile mark. Currently she’s drilled 20,637 feet with another 3,927 go -- just under 3/4 of a...
Friday Mar 19, 2021
Drop shaft work continues throughout the tunnel works program. Photos below taken this week -- on the left where we see drop shaft...
Friday Mar 12, 2021
MamaJo should be hitting the 4-mile mark later this month. Below left shows workers at drop shaft 5 (Thieme Drive) where progress continues...
Friday Mar 5, 2021
Work continues under and above ground on tunnel projects. Below at drop shaft 5 (Thieme Drive) iron worker install forms. Week of March...
Thursday Mar 4, 2021
One Mile To Go! Crews hit the milestone during second shift on March 3, 2021, making the remaining journey for MamaJo one mile. Below...
Thursday Feb 25, 2021
MamaJo continues her journey and is approaching the one-mile left to go mark. Along the route – work is on-going for our drop...
Friday Feb 19, 2021
For the second week in a row, heavy snow caused delays construction delays. Still, MamaJo, unaffected by the weather, continued moving 200 feet...
Friday Feb 12, 2021
A heavy snow and cold temperatures caused some delays this week especially where they were pouring concrete. Below on the left shows where...
Friday Feb 5, 2021
MamaJo has passed drop shaft 3 (Brown Street) and is just north of the Hale Avenue bridge today. This week saw 8-inches of...
Friday Jan 29, 2021
As MamaJo moves further away from her starting point near Dwenger and Glasgow Avenue, booster pumps are needed to keep the slurry lines...